The project manager contract grew by $110,886 as the project's budget rose from $2.9M to $7.5M; the renovation must be finished by October 31, 2026.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Apr 9, 2026.
Impact analysis
Contract rises to $349,832, within the $350,000 budget line.
Newport and Middletown residents who will use the renovated community center.
Tenants who had to relocate during construction — acknowledged by staff.
Mentions & discussions (2)
Newport City Council Budget Workshop- Resiliency & Sustainability - Apr 9, 2026
The $7.5 million upgrade of the Florence Gray Center is on time and on budget, with a certificate of occupancy expected at the end of August.
Newport City Council (Regular) - Jan 28, 2026
The project manager contract grew by $110,886 as the project's budget rose from $2.9M to $7.5M; the renovation must be finished by October 31, 2026.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Newport, RI
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.