Narragansett Avenue sidewalks and Transportation Master Plan delivery
Summary
The city has $500,000 set aside and a $4 million federal grant, but can't use the local money as the grant match if it's spent first. Waiting means better scope but a year-long delay for residents walking in the street.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Apr 14, 2026.
Impact analysis
A $4 million federal grant with an $800,000-plus local match, plus the $500,000 already budgeted.
Pedestrians, cyclists, and students traveling the Narragansett Avenue corridor, including Salve Regina and 40 Steps visitors.
If delayed, residents continue walking in the roadway for another year.
Mentions & discussions (2)
Newport City Council Workshop with the Bicycle & Pedestrian Advisory Commission- Live Stream Unavailable - Apr 14, 2026
The city has $500,000 set aside and a $4 million federal grant, but can't use the local money as the grant match if it's spent first. Waiting means better scope but a year-long delay for residents walking in the street.
Newport City Council (Regular) - Feb 11, 2026
Councilors Khamsyvoravong and Carlin blasted the delay in building the Narragansett Avenue sidewalk project, which was the reason they supported last year's budget. A $4 million Safe Streets for All grant is now covering much of it, but they threatened to vote against the FY27 budget if construction doesn't start this summer.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Newport, RI
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.