Water system dam inspections
The council added $32,950 in dam inspection work — visual and state-required reports on eight high-hazard dams in the drinking water system.
GoNetSpeed fiber broadband deployment
A new fiber internet option is live at 525 addresses with the full city build — about 4,621 locations — due by early 2027, including a $39.99/month low-cost plan and free library connections.
Ward 1 stormwater and Elizabeth Brook flooding
Councilor Carlin argued grant money would be better spent on flooding in Wards 1 and 2. Staff explained Ward 1's flooding is a different, stormwater-driven problem along Elizabeth Brook, with an eight-figure price tag, and the grant is geographically restricted to the Hazard Road area.
Chain-of-command question: utilities and public services reporting
Councilor Carlin said he regrets his earlier vote and thinks Public Services and Utilities should report directly to the city manager rather than through the Resilience and Sustainability director, citing communication and workload concerns.
Station 1 Water Treatment Plant Modernization
A $791K contract will modernize the drinking water plant's computer control systems — the invisible machinery keeping the tap water safe.